R815,01 Incl. VAT
Weight | 1200 g |
---|---|
Author | I Cruickshank, J Simm |
Publisher | ICE Publishing |
ISBN Number | 0727726862 |
Contents
Illustrations XXV
1. Introduction 1
1.1. The need to manage risks in coastal engineering construction, 1
1.2. Scope of coastal engineering works and materials, 3
1.2.1. Harbour breakwaters, 4
1.2.2. Coastal defence works, 4
1.2.3. Marine jetties and dolphins, 6
1.2.4. Navigational dredging works, 7
1.2.5. Intakes and outfalls, 7
1.3. Benefits and aims of risk management, 7
1.4. Objectives, readership, structure and use of this manual, 8
1.4.1. Objectives of the manual, 8
1.4.2. Readership of the manual, 10
1.4.3. Structure and use of the manual, 11
Part A 15
2. Protocol 17
2.1. General duties, 19
2.1.1. Duties of clients, 19
2.1.2. Duties of the designer, 20
2.1.3. Duties of the contractor, 22
2.2. Duties relating to different facets of the project process, 22
2.2.1. Project concept or inception, 22
2.2.2. Project programme, 24
2.2.3. Project design development, 25
2.2.4. Pre-qualification of contractors, 26
2.2.5. Preparation of tender documents, 27
2.2.6. Tender period, 31
2.2.7. Award of contract, 32
2.2.8. Construction period, 33
2.2.9. Post-construction, 34
Part B 35
3. Risk identification, modelling and management 37
3.1. Introduction, 37
3.2. The benefits of systematic risk management in coastal engineering, 39
3.3. Risk management at various stages of project development and implementation, 41
3.3.1. Design stage (client driven), 41
3.3.2. Pre-procurement stage (client driven), 43
3.3.3. Tender stage (contractor driven), 43
3.3.4. Construction (client and contractor driven), 43
3.4. Risk management procedure, 44
3.5. Risk definitions, 44
3.5.1. Risk, 44
3.5.2. Hazard, 47
3.5.3. Uncertainty, 48
3.6. Risk assessment approaches, 50
3.6.1. STEP 1 – Strategic business assessments, 51
3.6.2. STEP 2 – Identify the objectives of the risk assessment and the level of detail to be adopted, 52
3.6.3. STEP 3 – Identify hazards and risks, 52
3.6.4. STEP 4 – Consider the ownership of the risks, 53
3.6.5. STEP 5 – Assess the likelihood and consequences of these risks, 54
3.6.6. STEP 6 – Identify control/mitigation measures, 54
3.6.7. STEP 7 – Assess the residual risks including new risks that are created by the mitigation measures, 55
3.6.8. STEP 8 – Estimate the cost of mitigation measures, 55
3.6.9. STEP 9 – Estimate the net benefit of the measure, 57
3.6.10. STEP 10 – Select and implement beneficial mitigation actions, 57
3.6.11. STEP 11 – Monitor and review the process/feedback into the cycle, 57
3.7. Simple risk management tools, 58
3.7.1. Risk workshop, 59
3.7.2. Influence diagrams and rich pictures, 59
3.7.3. Likelihood-consequence tables, 60
3.7.4. Flow diagrams, 63
3.7.5. Decision/event tree, 64
3.7.6. Recording risk control strategies, 64
3.7.7. Risk calendar, 65
3.7.8. Sensitivity analysis, 65
3.7.9. Monte Carlo methods, 66
3.8. Evaluation of risks by contractors at tender stage, 69
3.9. Budgets and contingencies, 74
3.10. More complex tools (computational risk models), 77
3.10.1. Cost risk techniques, 77
3.10.2. Schedule risk techniques, 83
3.10.3. Scenario modelling, 88
3.10.4. Real-time modelling, 89
4. The uncertain sea 91
4.1. The basic parameters, 93
4.1.1. Wind climate, 93
4.1.2. Wave climate, 95
4.1.3. Tidal currents, 106
4.1.4. Water levels, 107
4.1.5. Joint probability of waves and water levels, 110
4.2. Methods of estimating site conditions, 111
4.2.1. Estimation of wind data, 111
4.2.2. Estimation of wave conditions at the site, 111
4.2.3. Estimation of water levels, 115
4.2.4. Estimation of currents, 121
4.3. Real time forecasting, 123
5. Coastal construction methods and risks 131
5.1. Coastal construction plant, operability levels and availability, 131
5.1.1. Plant types, 131
5.1.2. Plant operability, 142
5.1.3. Availability of staff, plant and facilities, 156
5.2. Temporary stability of works, 156
5.3. Construction tolerances, 166
5.4. Safety of the public and site personnel, 170
5.5. Sea bed and beach profile changes, 171
5.6. Uncertainty of ground conditions, 173
5.7. Uncertainty of condition of existing structures, 175
5.8. Reliability of materials’ supply, 177
5.9. Timing of works, 178
5.10. Access, 185
5.11. Variability of quantities, 187
5.12. Infilling of excavations and dispersal of spoil heaps, 192
6. Safety, health and the environment 193
6.1. Health and safety, 193
6.2. Safety legislation in the coastal environment, 194
6.2.1. Acts, 194
6.2.2. Regulations, 196
6.3. Safety enforcement in the coastal environment, 198
6.4. Current problems with health and safety in coastal engineering, 202
6.5. Common safety hazards in coastal engineering, 203
6.5.1. Working over/adjacent to water, 204
6.5.2. Cofferdams, 205
6.5.3. Earth moving plant, 205
6.5.4. Sea outfalls, 205
6.5.5. Diving, 205
6.5.6. Explosives underwater, 206
6.6. Safety risk assessment and integration with other risk assessments, 206
6.7. Environmental risks, 207
6.7.1. Noise, 207
6.7.2. Traffic, 209
6.7.3. Dredging and disposal, fisheries and compensation. 209
7. Insurance 219
7.1. Introduction, 219
7.1.1. Limitations of insurance as an option for covering a risk, 219
7.1.2. Glossary, 221
7.2. Risk management, 221
7.2.1. Evaluation of the risk, 222
7.2.2. Limits of Liability, 225
7.2.3. Levels of excess, 226
7.2.4. Division of risk – client or contractor, 227
7.3. Types of cover available, 229
7.3.1. Contractor’s All Risks & Erection All Risks, 230
7.3.2. Decennial Liability, 233
7.3.3. Marine Insurance, 234
7.4. Limitation of liability for vessels, 244
7.5. Specific problems in relation to coastal construction, 245
7.6. Use of specialists, 248
7.6.1. Specialists for identifying risks, 248
7.6.2. Specialists for identifying risks in respect of exclusions under a policy, 249
7.6.3. Loss Adjusters and Average Adjusters, 250
7.7. Advice to Underwriters, 251
7.7.1. Advice to Underwriters of changing risk during period of policy, 251
7.7.2. Advice to Underwriters of claims, 251
8. Procurement 263
8.1. Introduction – the objectives of a procurement strategy, 263
8.2. The client in coastal engineering, 266
8.2.1. The nature of the client, 266
8.2.2. Size and experience of the client, 267
8.3. Project Funding in Coastal Engineering, 269
8.3.1. The public sector, 269
8.3.2. Choice of an appropriate procurement strategy, 272
8.4. Selecting a procurement strategy, 276
8.5. Methods of Procurement – The Well Established Options, 277
8.5.1. Traditional, 277
8.5.2. Design and build, 278
8.5.3. Construction management,281
8.5.4. Management contracting, 282
8.6. A Procurement Strategy for Coastal Engineering, 283
8.6.1. The contract strategy, 284
8.6.2. Pre-qualification of tenderers, 296
8.6.3. Bid review, 298
8.6.4. Tender review, 298
8.7. Problems of Risk Perception, 299
8.8. Suggested Improvements in Risk Allocation within Tender Documents, 308
8.9. The Impact of Risk, 310
8.10. Procurement Strategies for the Future, 311
8.10.1. Project partnering, 316
8.10.2. Refine and build, 317
8.11. Conclusion, 319
Part C 321
9. Specific risks – introduction 323
9.1. Introduction, 323
9.2. Risk Identification, 323
9.2.1. Common ‘general’ risks, 324
9.2.2. Common risks related to structure types, 324
9.3. Risk evaluation, 325
9.4. Possible Risk Control Strategies, 325
9.4.1. Remove, 326
9.4.2. Reduce, 326
9.4.3. Transfer, 326
9.4.4.. Share, 327
9.4.5. Accept, 327
9.4.6. Insure, 328
9.5. Risk monitoring and review, 329
10. Rock works 335
10.1. Introduction, 335
10.2. Client’s project objectives, 335
10.3. Rock work types, 336
10.4. Rock sourcing – obtaining rock that complies with the specification, 338
10.5. Rock delivery, 341
10.5.1. Road delivery, 342
10.5.2. Rail delivery, 342
10.5.3. Sea delivery, 344
10.6. Rock placing, 354
10.6.1. General rock placing and buildability, 354
10.6.2. Availability of plant, 356
10.6.3. Stone variability and void ratio, 356
10.6.4. Ability to achieve rock profile, 358
10.6.5. Experience and flexibility of the client’s representative on site, 358
10.6.6. Variations in the formation line, 360
10.6.7. Stability of the incompleted works, 360
10.6.8. Settlement, 362
10.6.9. Wastage due to breakages, 362
10.6.10. Core material loss, 364
10.6.11. Barge beaching risks, 364
10.6.12. Damage to vessels, 366
10.6.13. Public safety, 366
10.6.14. Exchange rate risk, 366
11. Concrete armour units 371
11.1. Introduction, 371
11.2. Client’s project objectives, 374
11.3. Forming units, 374
11.3.1. Obtaining consent to use the unit, 3 74
11.3.2. Availability of moulds and inadequate numbers, 374
11.3.3. Land availability for unit production, 374
11.3.4. Cracking, 376
11.3.5. Transporting units, 376
11.4. Placing of units, 378
11.4.1. Achieving the placing specification, 378
11.4.2. Sea state, 378
11.4.3. Plant availability, 380
11.4.4. Public safety, 380
11.4.5. Timing of the works, 380
11.4.6. Stability of the incompleted works, 380
12. Concrete seawalls and revetments 387
12.1. Introduction, 387
12.2. Client’s project objectives, 387
12.3. Sea state, 390
12.4. Public safety, 390
12.5. Water levels, 390
12.6. Variation in existing structures, 392
12.7. Variation in beach levels, 392
12.8. Ground investigation, 392
12.9. Timing of the works, 394
12.10. Congestion, 394
13. Caisson works 399
13.1. Introduction, 399
13.2. Client’s project objectives, 399
13.3. Timing of the works, 400
13.4. Transportation of the caisson to position – waves, wind, water levels and currents, 400
13.5. Bed preparation, 402
13.6. Positioning, 402
13.7. Temporary instability of caisson, 402
13.8. Availability of temporary facilities, 404
13.9. Plant availability, 404
14. Coastal piling works 409
14.1. Introduction, 409
14.2. Client’s project objectives, 409
14.3. Sea state, 410
14.4. Ground conditions, 412
14.5. Plant availability, 412
14.6. Timing of the works, 412
15. Outfall and intake projects 417
15.1. Introduction, 417
15.2. Client’s Project objectives, 420
15.3. Timing of the works, 420
15.4. Materials, 422
15.5. Sea State, 422
15.6. Water levels, 424
15.7. Currents, 424
15.8. Considerations affecting dredged trench, 424
15.9. Plant and plant availability, 426
15.10.. Integrity of pipes during installation, 428
15.11.. Launch site, 428
15.12.. Diffuser Installation by drilling through sea bed, 430
15.13.. Public safety, 430
15.14.. Ground Investigation, 430
15.15.. Fishery aspects, 430
16. Navigational dredging works 435
16.1. Introduction, 435
16.2. Client’s project objectives, 436
16.3. General issues, 438
16.3.1. Timing of the works, 438
16.3.2. Weather and sea state, 438
16.3.3. Inadequate or inaccurate ground investigation, 438
16.3.4. Siltation and measurement, 440
16.3.5. Turbidity, 440
16.3.6. Fishery aspects, 440
16.3.7. Debris, 442
16.3.8. Side slopes, 442
16.3.9. Ordnance, 442
16.4. Dredging vessels, 444
16.4.1. Backhoe and grab dredging vessels, 444
16.4.2. Bucket chain dredging vessels, 446
16.4.3. Cutter suction dredging vessel, 447
16.4.4. Trailing suction hopper dredging vessels, 448
17. Beach nourishment 453
17.1. Introduction, 453
17.2. Client’s project objectives, 453
17.3. General Risks, 454
17.3.1. Timing of the works, 454
17.3.2. Material sourcing, specification and availability, 454
17.3.3. Disruption due to fishery aspects, 456
17.4. Delivery By Sea, 458
17.4.1. Sea State, 458
17.4.2. Water levels, 460
17.4.3. Currents, 462
17.4.4. Measurement, 462
17.4.5. Availability of plant and materials, 466
17.4.6. Restrictions on working hours, 466
17.4.7. Public safety, 468
17.4.8. Access availability, 470
17.5. Delivery by land, 472
17.5.1. Public safety, 472
17.5.2. Access availability, 472
18. References 477
Appendix 481
Index 491