R2900,00 Incl. VAT
| Weight | 1000 g |
|---|---|
| Author | Geoffrey Smith PS Consulting, France |
| Publication Date | December 2023 |
| Publisher | Emerald Publishing/ICE Publishing |
| ISBN | 9780727766526 |
| Contents | Preface | xi |
| About the author | xiii | |
| Glossary | xv | |
| Abbreviations | xxvii | |
| 01 | Introduction | 1 |
| 02 | Setting the scene | 5 |
| 2.1 Introduction | 5 | |
| 2.2 Contract Data | 6 | |
| 2.3 Special Provisions | 8 | |
| 2.4 Specifications, Drawings and Employer’s Requirements | 10 | |
| 03 | The basics | 13 |
| 3.1 Definitions | 13 | |
| 3.2 Notices and Communications | 17 | |
| 3.3 Law and Language | 22 | |
| 3.4 Priority of Documents | 23 | |
| 3.5 Contract Agreement | 26 | |
| 3.6 Joint Ventures | 26 | |
| 3.7 Limitation of Liability | 27 | |
| 04 | Basic obligations of the employer | 29 |
| 4.1 Introduction | 29 | |
| 4.2 Provision of the Site | 29 | |
| 4.3 Assistance with respect to permits, copies of Laws | ||
| and so forth | 32 | |
| 4.4 Employer’s Personnel and Other Contractors | 32 | |
| 4.5 Financial Arrangements | 33 | |
| 4.6 Site Data | 35 | |
| 05 | The role of the engineer/employer’s representative | 39 |
| 5.1 The Person | 39 | |
| 5.2 Authority | 40 | |
| 5.3 Delegation | 41 | |
| 5.4 Instructions | 43 | |
| 5.5 Determinations | 45 | |
| 06 | Basic obligations of the contractor | 57 |
| 6.1 Introduction | 57 | |
| 6.2 General Obligations | 57 | |
| 6.3 Resources | 58 | |
| 6.4 Methods of working | 58 | |
| 6.5 Contractor’s Representative | 59 | |
| 6.6 Key Personnel | 60 | |
| 6.7 Contractor’s Personnel | 61 | |
| 6.8 Contractor’s Superintendence | 62 | |
| 6.9 Contractor’s Equipment | 62 | |
| 6.10 Goods | 62 | |
| 6.11 Contractor’s Records and Progress Reports | 64 | |
| 6.12 Cooperation and coordination | 67 | |
| 6.13 Health and safety | 68 | |
| 6.14 Environment | 71 | |
| 6.15 Code of Conduct | 72 | |
| 6.16 Management Strategies and Implementation Plans | 73 | |
| 6.17 Subcontractors, Nominated Subcontractors and Suppliers | 74 | |
| 07 | Design | 81 |
| 7.1 Employer’s design | 81 | |
| 7.2 Employer’s Requirements | 83 | |
| 7.3 Design by Contractor | 86 | |
| 7.4 Preparation and processing of Contractor’s Documents | 89 | |
| 7.5 As-Built Records and Operation and Maintenance | ||
| Manuals | 92 | |
| 7.6 Training | 95 | |
| 08 | Project start-up | 97 |
| 8.1 Performance, Environmental and Social Performance, | ||
| and Advance Payment Securities | 97 | |
| 8.2 Advance Payment | 102 | |
| 8.3 Notice of Commencement | 103 | |
| 8.4 Means of access and additional working areas | 108 | |
| 8.5 Permits | 109 | |
| 8.6 Mobilisation | 109 | |
| 8.7 Checklist for Commencement of Works | 110 | |
| 09 | Quality | 113 |
| 9.1 Quality Assurance | 113 | |
| 9.2 Samples | 114 | |
| 9.3 Inspections | 115 | |
| 9.4 Tests (other than the Tests after Completion) | 116 | |
| 9.5 Defects and Remedial Work | 118 | |
| 10 | Timing | 121 |
| 10.1 Contractor’s Programme | 121 | |
| 10.2 Time for Completion | 123 | |
| 10.3 Advance Warnings | 123 | |
| 10.4 Monthly reports | 124 | |
| 10.5 Delay Damages | 125 | |
| 10.6 Intermediate Milestones | 126 | |
| 10.7 Extensions of Time | 128 | |
| 10.8 Concurrent delay | 129 | |
| 10.9 Delays Caused by Authorities | 130 | |
| 10.10 Suspensions instructed by the Engineer/Employer | 131 | |
| 10.11 Rate of Progress | 133 | |
| 10.12 Acceleration | 133 | |
| 11 | Completion of the works | 135 |
| 11.1 Tests on Completion | 135 | |
| 11.2 Taking Over | 143 | |
| 11.3 Tests after Completion | 147 | |
| 11.4 Defects Notification Period | 150 | |
| 11.5 Completion of Outstanding Work and | ||
| Remedying Defects | 151 | |
| 11.6 Cost of Remedying Defects | 151 | |
| 11.7 Extension of Defects Notification Period | 152 | |
| 11.8 Failure to remedy defects | 153 | |
| 11.9 Remedying of Defective Work off Site | 153 | |
| 11.10 Further Tests after Remedying Defects | 154 | |
| 11.11 Right of Access after Taking Over | 154 | |
| 11.12 Searching for the cause of a defect (root cause | ||
| investigation) | 154 | |
| 11.13 Performance Certificate | 155 | |
| 11.14 Legal liability for defects | 156 | |
| 12 | Payments | 159 |
| 12.1 Contract Price | 159 | |
| 12.2 Preparation of Statements | 162 | |
| 12.3 Retention | 170 | |
| 12.4 Advances for Materials on Site | 172 | |
| 12.5 Interim Payment Certificate | 174 | |
| 12.6 Payments | 178 | |
| 12.7 Currencies of Payment | 179 | |
| 12.8 Late payment | 180 | |
| 12.9 Statement at Completion | 181 | |
| 12.10 Final Statement | 182 | |
| 12.11 Discharge, Final Certificate and Final Payment | 183 | |
| 12.12 Cessation of Employer’s Liability | 188 | |
| 13 | Variations and adjustments | 189 |
| 13.1 Right to Vary | 189 | |
| 13.2 Variation by Instruction | 191 | |
| 13.3 Variation proposals | 192 | |
| 13.4 Value Engineering | 193 | |
| 13.5 Valuation of the Variation | 193 | |
| 13.6 Omissions | 195 | |
| 13.7 Dayworks | 196 | |
| 13.8 Provisional Sums | 196 | |
| 13.9 Adjustments for major changes in quantity | 197 | |
| 13.10 Adjustments for changes in legislation | 198 | |
| 13.11 Adjustments for Changes in Cost | 199 | |
| 14 | Suspension and termination | 205 |
| 14.1 Termination by the Employer due Contractor’s | ||
| default | 205 | |
| 14.2 Termination by the Employer “for convenience” | 209 | |
| 14.3 Suspension by the Contractor | 211 | |
| 14.4 Termination by the Contractor due Employer’s | ||
| default | 212 | |
| 15 | Contractor’s care of the works, employer’s risks, | |
| exceptional events | 219 | |
| 15.1 Contractor’s care of the Works | 219 | |
| 15.2 Employer’s Risks | 219 | |
| 15.3 Indemnities | 221 | |
| 15.4 Exceptional Events | 222 | |
| 15.5 Release from Performance under the Law | 224 | |
| 16 | Insurances | 227 |
| 17 | Claims | 231 |
| 17.1 Notice of Claim | 237 | |
| 17.2 Response to the Notice of Claim | 238 | |
| 17.3 Contemporary Records | 238 | |
| 17.4 Fully detailed Claim | 239 | |
| 17.5 Claims of continuing effect | 241 | |
| 17.6 Agreement or determination of the Claim | 243 | |
| 17.7 General requirements | 245 | |
| 18 | Disputes | 247 |
| 18.1 Background | 247 | |
| 18.2 DAAB appointment | 248 | |
| 18.3 Replacement of DAAB Member | 248 | |
| 18.4 Failure to agree on appointment | 248 | |
| 18.5 DAAB Agreement | 249 | |
| 18.6 DAAB Procedural Rules | 250 | |
| 18.7 Notice of Effective Date | 250 | |
| 18.8 Warranties/Declaration of Independence | 251 | |
| 18.9 General Obligations | 252 | |
| 18.10 Indemnities | 253 | |
| 18.11 Remuneration | 253 | |
| 18.12 Failure to agree fees | 254 | |
| 18.13 Resignation of the DAAB Member | 254 | |
| 18.14 Termination of the DAAB Member | 255 | |
| 18.15 Effects of resignation or termination | 255 | |
| 18.16 Challenges | 255 | |
| 18.17 Duration of DAAB Agreement | 258 | |
| 18.18 Communications | 258 | |
| 18.19 Site visits and meetings | 259 | |
| 18.20 Avoidance of Disputes | 261 | |
| 18.21 Powers of the DAAB | 262 | |
| 18.22 Reference of a Dispute to the DAAB | 263 | |
| 18.23 Hearings | 264 | |
| 18.24 Decisions | 265 | |
| 18.25 Amicable Settlement | 268 | |
| 18.26 Compliance | 268 | |
| 18.27 Arbitration | 269 | |
| 18.28 No DAAB in place | 270 | |
| 18.29 World Bank Special Provisions | 271 | |
| 19 | The 2022 reprint | 273 |
| 19.1 Background | 273 | |
| 19.2 The definition of ‘Claim’ | 273 | |
| 19.3 The definition of ‘Dispute’ | 275 | |
| 19.4 Clarifications with respect to ‘Part(s)’ | 276 | |
| 19.5 Errors in Setting Out reference items | 276 | |
| 19.6 Contractor’s Discharge | 277 | |
| 19.7 The appointing official | 277 | |
| 19.8 Referral to the DAAB of a deemed rejection by | ||
| the Engineer | 278 | |
| 19.9 General Conditions of DAAB Agreement and | ||
| DAAB Procedural Rules | 279 | |
| 19.10 Notes on the Preparation of Special Provisions | 279 | |
| Annex 1 – Code of conduct for contractor’s | ||
| personnel (ES) form | 281 | |
| Annex 2 – Significant changes in the 2022 reprint | 285 | |
| Index | 311 |