R2500,00 Incl. VAT
Weight | 1200 g |
---|---|
Author | A.Hamilton |
Publisher | ICE Publishing |
ISBN Number | 0727729411 |
Year | 2001 |
Contents
List of tables vii
List of figures viii
Preface ix
Acknowledgements xii
List of abbreviations xiv
PART 1: THE FRAMEWORK 1
Chapter 1 Change: using it to our advantage 3
Chapter 2 Management: the means to transform 21
Chapter 3 Systems theory 33
Chapter 4 Systems mapping 51
Chapter 5 Projects: one-time events 68
Chapter 6 Project management process 90
Chapter 7 Project scope management and time management 107
Chapter 8 Project cost management and communication management 127
Chapter 9 Project risk management and procurement management 144
Chapter 10 Project human resources management and quality management 163
Part 1 References 178
PART 2: PLANNING FOR CONTROL 183
Chapter 11 Planning the project 185
Chapter 12 Scheduling methods 204
Chapter 13 Network scheduling 228
Chapter 14 Precedence diagramming and scheduling 243
Chapter 15 Resource allocation 255
Chapter 16 Least-cost scheduling 276
Chapter 17 Program evaluation and review technique 294
Chapter 18 Work progress and updating 310
Chapter 19 Project time and cost control 329
Chapter 20 Tracking and analysing delays 343
Part 2 References 358
PART 3: THE TOOL KIT 361
Chapter 21 Conceptualising the project 363
Chapter 22 Economic evaluation and funding 381
Chapter 23 Defining the project 400
Chapter 24 The value process 416
Chapter 25 Concurrent engineering and configuration management 442
Chapter 26 Risk identification, analysis and allocation 462
Chapter 27 Cost estimation methods 488
Chapter 28 Procuring goods and services 506
Chapter 29 The project team and its management 531
Chapter 30 Implementation and close-out 557
Part 3 References 573
Reading list 577
Index 579
List of tables
1-1 Characteristics of the two hemispheres of the human brain 11
3-1 Comparison of the analytical approach and the systems approach 36
4-1 Some components of systems 61
12-1 Lower full activity, with reference to Figure 12-8 218
15-1 Tabulating project network and resource data 268
16-1 A worksheet for an example project 289
17-1 The central limit theorem 305
18-1 Values of total earnings or expenditure 320
18-2 Trend analysis 322
18-3 Variance of activity performance factor 323
18-4 The importance of subcontractor A to completion 325
19-1 Budget cost of work scheduled compared with budget cost of
work performed and actual cost of work performed 337
21-1 Scoring options or alternatives 275
22-1 Cashflow 384
22-2 Sensitivity testing – initial cost plus 30% 393
22-3 Sensitivity testing – no salvage value 393
22-4 Comparison of alternatives 398
23-1 Costs and saving (in monetary units) 405
23-2 A progress measurement system 407
24-1 Function costs 430
24-2 Information relative to Table 24-3 436
24-3 Calculation of life-cycle costs 436
25-1 Some tools and their outcomes 448
26-1 Some major sources of risk 468
26-2 Duration, probability and expected value 472
26-3 Triangular and beta distributions 474
26-4 Information relative to Figure 26-6(a) 475
26-5 10 x 10 array of three-digit random numbers 476
26-6 A range of risk measures 479
27-1 Template for improved cost estimation 499
27-2 A summary of operating cost estimates 503
28-1 An example of prequalification evaluation 511
29-1 A questionnaire for discovering areas of strength and weakness 553
Li st of figures
1-1 Rate of change in social development 5
1-2 Structure of the brain 9
3-1 Organisational systems and its management 45
4-1 Feedback loop 55
4-2 Reinforcing loop 56
4-3 Balancing feedback 57
4-4 Components of systems maps 62
4-5 Components of influence diagrams 63
4-6 Components of multiple cause diagrams 65
4-7 Components of sign-graph diagrams 66
5-1 Project examples 73
6-1 Triple constraints 94
6-2 Project management processes 101
6-3 Processes within a project or a phase 103
7-1 Project scope management processes 109
7-2 Project time management processes 116
7-3 AON and AOA diagrams 118
7-4 Sequence of significant scope and time outputs 124
7-5 Different dependency relationships 126
8-1 Project cost management processes 129
8-2 Project communications management processes 136
8-3 Sequence of significant cost and communication outputs
(scopes = time outputs shown) 141
9-1 Project risk management processes 147
9-2 Project procurement management processes 153
9-3 Sequence of significant risk and procurement outputs 160
10-1 Project human resources management processes 165
10-2 Project quality management processes 169
11-1 Project management processes with time 188
11-2 An example of a tree-like WBS 191
11-3 A very small section of a project = s RAM 194
11-4 Activity sequencing terminology 196
11-5 Best practice in crossing dependency lines 197
11-6 A solution to Exercise 11-3 202
12-1 Basic type of bar chart 208
21-2 Linked activity bar chart 209
21-3 (a) & (b) Bar charts for combined activities and milestones 209
12-4 Partial relationship chart 210
12-5 LOB x-axis 213
12-6 LOB using only start buffers 214
12-7 (a) LOB using start and finish buffers; (b) Completed LOB
diagram 215
12-8 Time-chainage chart 217
12-9 (a), (b), (c) & (d) Arrow diagram notation 220
12-10 Sloping format 221
12-11 Staff format 222
12-12(a) & (b) Dummy activities 222
12-13(a) & (b) Dummy activities relative to node numbering 223
12-14Use of cross-over symbols 223
12-15 Example of AOA diagram 224
12-16 Example of AON diagram 224
12-17A solution to Exercise 12-1 226
12-18 A solution to Exercise 12-2 227
12-19A solution to Exercise 12-3 227
13-1 Planning levels 231
13-2 Typical node box 232
13-3 Example of node network 233
13-4 A forward pass 234
13-5 A backward pass 236
13-6 The revised node 237
13-7 More than one successor 237
13-8 A solution to Exercise 13-1 240
13-9 A solution to Exercise 13-2 241
13-10A solution to Exercise 13-3 241
13-11 A solution to Exercise 13-4 242
14-1 A solution to Exercise 14-1 253
14-2 A solution to Exercise 14-2 253
15-1 Resources indicated 259
15-2 More than one resource 259
15-3 Separate resource histograms 260
15-4 Operatives (1) 263
15-5 Critical activities only 264
15-6 Operatives (2) 265
15-7 Rescheduled 266
15-8 Seven days 269
15-9 Eleven days 269
15-10Part schedule 270
15-11 Levelling completed 271
15-12Network analysis of Exercise 15-4 273
15-13 Bar chart interpretation 274
15-14Resource usage histogram 274
16-1 Cost breakdown structure 284
16-2 Time-cost relationship 287
16-3 Network analysis of Exercise 16-4 292
16-4 Tabulated worksheet of least cost 293
17-1 Work sequence 297
17-2 (a) Frequency histogram and (b) probability distribution 299
17-3 Activity time centrality and variability 300
17-4 Example of time-based network 305
17-5 Table of cumulative probabilities 306
18-1 Progress earnings/payments profile 321
19-1 Cost baseline 334
19-2 A planning and scheduling hierarchy 341
20-1 Example network 351
20-2 As-planned bar graph 351
20-3 As-built bar graph 351
20-4 Adjusted as-built bar chart 353
20-5 Adjusted bar chart excluding non-excusable delays 354
20-6 Adjusted bar chart excluding compensable delays 354
20-7 Adjusted bar chart excluding concurrent compensable and
non-excusable delays 354
20-8 Adjusted bar chart excluding concurrent and excusable delays 355
21-1 A classification of production systems 365
21-2 Simplified evaluations and selection process 370
21-3 An optimal scheme process 371
22-1 Graphical cashflow 385
22-2 Patterns of cashflow 388
22-3 Net present value diagram 389
22-4 An internal rate of return graph 390
22-5 Sensitivity testing – change in discount rate 394
23-1 Design flow diagram for sub-project #1 406
23-2 An example of activity control points 407
23-3 Project procurement management process 409
23-4 Up-front project deliverables 413
24-1 Six-stage value engineering process 418
24-2 When to apply the value process 420
24-3 Typical cost model template 427
24-4 Decreasing cost histogram 429
24-5 Cost:worth comparison 431
24-6 FAST diagram template 432
24-7 Example of a technical FAST diagram 433
24-8 Standard form for logging ideas 434
24-9 Illustration of criteria weighting 437
24-10 Analysis matrix 438
24-11 A solution to Exercise 24-4 441
25-1 Technology management life phases 444
25-2 Classifying technological projects 445
25-3 Effect of delay in ) getting to market = 447
25-4 House of quality 449
25-5 Example of QFD application 450
25-6 CM flow diagram for early project phases 453
25-7 Project trend report form 456
25-8 Project change notice form 457
26-1 The range of uncertainty 464
26-2 Window of opportunity 465
26-3 Categories of risk 466
26-4 Up-front project planning 467
26-5 Brainstorming process 470
26-6 Developing/using a probability distribution 471
26-7 Decision tree 473
26-8 Six-step Monte Carlo process 474
26-9 Spider diagram 477
26-10 A solution to Exercise 26-2 486
27-1 Estimating type versus accuracy range 493
27-2 Examples of cost-capacity relationships 496
27-3 Typical breakdown of a project = s capital cost 498
27-4 Cumulative probability chart 501
28-1 Procurement activities 508
28-2 A simple purchase order template 510
28-3 Template for registering procurement status 512
28-4 Model expediting report 513
28-5 Template for materials received 515
28-6 A range of contractual approaches 517
28-7 A partnering process flow diagram 523
28-8 A selection of project team groupings 526
29-1 Functional organisation structure 535
29-2 Project organisation structure 536
29-3 Project matrix structure 536
29-4 Selecting the form of project organisation 539
29-5 The role of the project manager 542
29-6 Conflict process 546
29-7 Conflict intensity versus project phase 548
30-1 An integrated meetings/reports system 560
30-2 The last step – lessons learned 569